This article aims to highlight the purpose and consequence of breach of contract
in general and repudiatory breach of contract in specific. This article also
takes into account common law principles and cases to better understand the
Indian stand on this specific aspect. Contract is a document or an agreement
which is legally enforceable and binding on parties to the contract.
Anything
done contrary to the said terms of contract or any deviation or omission of any
contractual obligations enshrined in the contract leads to a breach of contract.
Breach of contract is a huge concept in the field of law. Each day there are
millions of cases filed for breach of contract, not just in India but in almost
every nation with a civilised legal system.
This article moves to highlight that
a breach of contract is not a narrow singular concept, there are different
classifications within a breach of contract, out which repudiatory breach of
contract which is prevalent in the current trend of modern breach of contract is
dealt in detail in this article.
Introduction
An agreement enforceable by law is a contract1. Pursuant to Section 2(e) of the
Indian Contract Act, 1872 Every promise and every set of promises, forming the
consideration for each other, is an agreement. When a person has failed to
perform or abstain from performing something as specified in their promise which
forms a legally enforceable agreement, is said to have breached the contract. In
other words, according to Cornell Law School's Legal Information Institute
Breach of Contract is:
"The violation of a contractual obligation. One may breach
a contract by repudiating a promise, failing to perform a promise, or
interfering with another party's performance.2 Not all breaches of contract are
similar to each other, there are different types of breach with different result
of consequences when the contract is breached. In this article I'll be covering
in detail the Repudiatory breach of contract.
In India, the consequences of a Breach of Contract are Compensation for the
damaged party which includes both liquidated and unliquidated damages, enforcing
Specific Performance on the breaching Party, Imposition of injunction against
the breaching party and/or making the contract void. Repudiatory breach is one
of the underlying principles to terminate a contract validly.
It simply means a
contravention of a stipulated situation which goes so much into the root of the
contract that it makes further commercial performance of a contract
impossible.3Where one party to a contract indicates by words or through conduct
that he does not intend to perform his obligations, he is said to have
repudiated the contract by his actions4
In the case of
White and Carter v. Mcgregor 5 It was held by the House of Lords
that if one party to a contract repudiates it in the sense of making it clear to
the other party that he refuses or will refuse to carry out his part of the
contract, the other party, the innocent party, has an option. He may accept that
repudiation and sue for damages for breach of contract, whether or not the time
for performance has come; or he may if he chooses disregard or refuse to accept
it and then the contract remains in full effect. The Supreme Court of India has
taken the same principle enunciated in the above case[
White and Carter v. Mcgregor ]and reiterated in various cases including the case of
State of Kerala
v. C.C. Refineries 6, ,and many more7.
If the innocent party elects to keep the contract alive, he is said to have
'affirmed' the contract. The house of lords in the White and Carter case8, held
that the contract had remained intact after the breach of contract and that the
innocent party even though he chose to continue the contract was entitled to sue
for the contract price. But the obiter dicta of the same case by Lord Reid
stated the innocent party may not elect to keep the contract alive where he has
"no substantial or legitimate interest" in completing the performance and that,
in such cases, the innocent party's only remedy is in the form of damages.
The
principle of legitimate interest was enunciated in the Madras high court case of
Simplex Infrastructure Limited v. Aban Offshore Ltd.,9 which took reference to
the White and Carter case10 held "if a person has no legitimate interest in
performing the contract rather a sole intention of claiming damages, then he
ought not to be allowed to claim the same from the other party".
The innocent
party was not entitled to claim compensation for the entire period of contract,
the party was only entitled to claim compensation until the date of institution
of proceedings. Conversely, Termination of Contract is one of the most common
consequences of a repudiatory breach of contract.
Does non compliance to the terms of contract by the innocent party after a
repudiatory breach performed by the breaching party lead to breach of
contractual obligation by the innocent party?
This type of situation arise when the innocent party opts to terminate the
contract and decides not to follow or omits the performance of certain
contractual obligation enumerated in the contract for its termination due to the
repudiatory breach performed by the breaching party , for instance non
compliance to the mandatory notice period before termination, or other
formalities enumerated in the contract for the termination of contractual
obligation between the two parties. Different courts of India have given its
interpretation and judgement regarding the said issue.
For example, In the case of
Air India Ltd. V. Gati Ltd.11A single judge bench of
the Delhi High Court has held "in case of Repudiatory Breach by one party,
termination of contract by another party is justified even if the procedure is
not followed". In the above mentioned case, the court has held that the
breaching party, i.e the person who committed the repudiatory breach cannot come
to court seeking damages for non compliance of the contractual term by the other
party after the the commission of the said repudiatory breach which makes the
commercial performance of a contract practically impossible to perform.
In an earlier judgement of the Himachal Pradesh High Court, in the case of
Deva
Builders vs. Nathpa Jhakri Joint Venture12 The court opined that even though the
respondent did not comply with the terms of the contract by not giving requisite
notice before terminating the contract, it was the plaintiff who in the first
instance breached the terms of the contract by not executing the work in
accordance with the terms and conditions of the agreement. And therefore it was
held, the plaintiff in the above mentioned case cannot claim damages for the
breach of contract by the respondent. I.e not giving requisite notice for
termination.
Similar judgement was also held by a two judge bench of the Gujarat High Court
in the case of D.L.F. Universal Ltd. vs. Atul Limited13 which stated, " In view
of the inordinate delay or inaction by the appellant and the fact that the
appellant had not performed its part of the contract, the procedure for
termination of contract agreed under Clause 10 of the agreement had become
superfluous.
The termination of agreement was on account of abandonment of the
contract by the appellant. The appellant did not suffer any damage on account of
termination of the contract. We do agree that the procedure for termination of
contract agreed under the agreement had been, under the circumstances, reduced
to a mere formality. The appellant did not suffer any prejudice for
non-adherence to the agreed procedure."
What if the other party to a contract is not at fault for the breach of
contract?
There can exist a situation where the terms of the contract cannot be complied
with, with no fault of either parties to the contract. Frustration of contract
and Force Majeure are some circumstances that will be dealt with in this article
regarding non performance of contract with no breach by either party to a
contract.
- Force Majeure
'Force Majeure' clause is a provision in a contract that exempts a party from
performing his contractual obligations which have become impossible or
impracticable due to an event or effect which the parties could not have
foreseen or controlled. This clause is usually articulated in general, inclusive
terms to cover unforeseeable incidents such as natural calamities, war, sudden
change of government policies etc.
It is pertinent to mention that the age old Indian Contract Act,1872 which was
introduced into the Indian legislature by the then British government governing
contracts in India does not expressly refer to 'Force Majeure' in any of its
clauses. However, the Real Estate (Regulation and Development) Act, 2016
includes a definition of 'Force Majeure' in its explanation to Section 514 as
follows:
Explanation For the purpose of this section, the expression "force majeure"
shall mean a case of war, flood, drought, fire, cyclone, earthquake or any other
calamity caused by nature affecting the regular development of the real estate
project.
- Doctrine of Frustration
The crux of this doctrine can be found in the common law judicial decision of
Taylor vs. Caldwell15. Prior to this decision, the law of contracts in England
was extremely cast-iron. No matter what the circumstances [Unforeseen or
otherwise] which renders the performance of a contract impossible, nevertheless
a contract had to be performed . This rigidity was somewhat relaxed by the
decision in Taylor vs. Caldwell in which it was held that if some unforeseen
event occurs during the performance of a contract which makes it impossible of
performance, in the sense that the fundamental basis of the contract goes, it
need not be further performed, as insisting upon such performance would be
unjust.
Unlike in England, the Doctrine of Frustration which was introduced as a
consequence of Judicial Decision, in India, there is a clear distinct principle
to deal with the doctrine of frustration which is enshrined in the Indian
contract Act itself. Section 56 of the Indian Contract Act states "An agreement
to do an act impossible in itself is void." Furthermore, Judicial decisions of
different courts of India have also thoroughly analysed and interpreted the said
doctrine to better understand the concept. For instance, in the case of
Satyabrata Ghose v. Mugneeram Bangur & Co.16 A three judge bench of the Hon'ble
Supreme Court of India held "A contract which has become impossible to perform
is said to be frustrated."
Reference:
- Indian Contract Act, 1872 Section 2(h)
- https://www.law.cornell.edu/wex/breach_of_contract
- VIACOM 18 Media Pvt. Ltd. vs. MSM Discovery Pvt. Ltd. MANU/TD/0199/2011
- Stephen A. Smith, Atiyah's Introduction to the Law of Contract (6th ed. 1995), p. 201
- WHITE AND CARTER (COUNCILS) LTD. APPELLANTS; AND MCGREGOR RESPONDENT., [1962] A.C. 413
- State of Kerala v. Cochin Chemical Refineries Ltd., (1968) 3 SCR 556
- Motilal Srinivasa Sarda v. Netha Co-operative Spinning Mills Ltd., 1974 SCC OnLine AP 159
- Ibid 5
- Simplex Infrastructure Limited v. Aban Offshore Ltd., 2021 SCC OnLine Mad 1676
- Ibid 5
- Air India Ltd. v. Gati Ltd., 2015 SCC OnLine Del 10220
- 2002(3)ShimLC11
- 2010(Suppl. 1)ArbLR362(Gujarat) / (2010)51GLR762
- The Real Estate (Regulation and Development) Act, 2016, Section 5
- (1861-73) All ER Rep 24
- Satyabrata Ghose v. Mugneeram Bangur & Co., 1954 SCR 310
Please Drop Your Comments