In contract law, when a contract is broken, the wronged party can receive
financial compensation, known as damages. These damages are categorized as
either liquidated or unliquidated, a key distinction in understanding legal
remedies for breach of contract. This explanation will explore these two types
of damages, showing examples and analysing their implications.
Liquidated Damages
-
Definition:
Liquidated damages are a pre-set sum of money that the contracting parties agree will be paid if the contract is breached.
This amount is determined when the contract is made, usually before signing. Ideally, it represents a reasonable estimate
of the potential losses resulting from a breach.
-
Purpose:
The purpose of liquidated damages is to offer predictability and avoid lengthy legal battles over compensation.
For instance, in construction contracts, a penalty of a certain amount per day of delay might be stipulated
if the contractor fails to meet the completion deadline.
-
Example of Liquidated Damages:
-
Suppose a company hires a contractor to build something within 12 months. The contract states that for every day
the contractor is late, they must pay $500 in liquidated damages. If the project is finished two weeks late,
the company receives $7,000 (14 days x $500). This predetermined financial consequence avoids disputes about the
company's actual financial loss.
-
When are Liquidated Damages Enforceable?
-
Courts will enforce liquidated damages clauses if they are considered a reasonable estimate of the actual
damages caused by a breach.
-
The predetermined amount must not be too high; otherwise, it might be considered a penalty rather than
a true estimate of loss.
-
If the liquidated damages sum far exceeds the expected harm from the breach, the clause might be deemed unenforceable
by a court. In that scenario, it is considered a penalty, and the injured party can only recover their actual losses
through unliquidated damages.
What are Unliquidated Damages?
Unliquidated damages, in contrast, are not predetermined. Instead, a court
assesses them after a breach occurs. These damages are based on the actual
losses suffered by the party who was not in breach. Unliquidated damages offer
more flexibility since the court considers the particular circumstances of the
case to determine fair compensation.
The calculation of unliquidated damages involves factors like the nature of the
breach, the extent of loss, and any mitigating circumstances to compensate the
injured party for the actual harm caused.
Example of Unliquidated Damages:
Imagine a supplier fails to deliver goods as contracted. The buyer loses
business because they cannot meet customer orders. The buyer can claim
unliquidated damages for lost profits and the business disruption caused. Unlike
liquidated damages, the amount is not fixed and depends on the actual financial
impact of the breach on the buyer's business.
Distinguishing Between Liquidated and Unliquidated Damages:
The primary difference lies in the timing of when damages are decided and how
they're calculated. Liquidated damages are agreed upon before the contract is
signed, providing certainty, whereas unliquidated damages are determined after a
breach happens based on actual losses.
Another key difference is that liquidated damages are designed to avoid the
difficulty of proving actual losses when such estimates are hard to establish.
Unliquidated damages require the injured party to prove the extent of their loss
and demonstrate that the claimed damages are reasonable.
Advantages of Liquidated Damages:
Certainty is a major benefit of liquidated damages. Both parties know in advance
the financial consequences of a breach and can better plan and manage risk,
particularly in industries where delays can cause significant financial harm.
Liquidated damages also save time and legal costs because parties don't have to
prove the extent of their loss. This efficient process makes them attractive for
contracts in construction, real estate, and event management.
It's also difficult to prove the exact amount of loss, especially when a breach
causes knock-on or indirect effects. Figuring out unliquidated damages might
involve getting experts involved and presenting a lot of detailed proof, making
things more complicated in court.
Conclusion:
Ultimately, liquidated and unliquidated damages are used for different purposes
in contract law. Liquidated damages, being a pre-agreed amount, offer certainty
and are often a practical choice for commercial deals. But they might not always
match the true extent of the damage. Unliquidated damages, though more flexible,
are based on the real losses and are decided by a court, but you need to prove
the harm you suffered. Both choices have their pros and cons. Which you use
depends on the details of the contract and what kind of breach happened.
Written By: Md.Imran Wahab, IPS, IGP, Provisioning, West Bengal
Email:
[email protected], Ph no: 9836576565
Also Read:
Please Drop Your Comments